Payment claim review: written position
Sample Fitout Pty Ltd. Subcontract to a builder, NSW. Made-up job.
The dates
- Claim served, $64,200
- Mon 2 Nov 2026
- Your email
- Last day for a schedule
- Mon 16 Nov 2026
- s 14(4)(b)
- Schedule received, $18,000
- Fri 13 Nov 2026
- Builder's email
- Last day to apply for adjudication
- Fri 27 Nov 2026
- s 17(3)(c)
What the record shows
Supported: $41,000 of base work, with photos and inspection records. Weak: $9,400 of variations with a verbal instruction and nothing in writing. Time to check: $13,800 of variation work, where the notice clause in your contract may be in play.
Your options
- If you decide to apply for adjudication: the last day on these facts is Fri 27 Nov 2026. The application is yours or your lawyer's to lodge. We don't act for you in adjudication.
- If you decide to negotiate first: the date above keeps running while you talk.
- If you decide to accept the schedule: the $18,000 is due by the due date, and the disputed amount stays unpaid unless it is raised again in a way your contract and the Act allow.