What happened. The owner of a specialist trade business was running everything himself, with no view of margin by job, no cash-flow forecast and cash tight.
Why it mattered. The books showed a profit but not which jobs made it, so a cash squeeze could arrive before anyone saw it coming.
The lesson. Control starts with seeing the numbers by job, before the month is out.
What we did. One team worked across the business: a scored diagnostic, a 12-month cash-flow forecast, a rebuilt chart of accounts, a contract review, variation claims, tender reviews, inspection plans and forms.
What came of it. On the variation claims, the builder's payment schedules showed nothing certified against variations on the first three claims, and more than $300,000 by the sixth. The rest of the work is still going.
33 + 42
Two trade owners, each on a full written diagnostic
What happened. Two trade owners were running the business through themselves. Quoting, invoicing and the big decisions all came back to the owner, and neither had a cash-flow forecast.
Why it mattered. One was running on an overdraft and only knew a job had made money after it finished. The other had no view of cost by job and no regular review of the numbers.
The lesson. An owner can't fix every part at once. A score against evidence shows which part to fix first.
What we did. We scored each business across six parts against evidence and wrote it up in full: 33 pages for one, 42 for the other, each with its red flags and a 90-day roadmap.
What came of it. One owner went on to 90 days of advisory work on the findings. The other has the report and the plan.
19 pages
A design-and-construct tender, before pricing
What happened. A subcontractor was about to price a large design-and-construct tender off a document pack that was inconsistent and partly out of date.
Why it mattered. On design and construct, whatever the documents leave unclear becomes the subcontractor's risk once the price is in.
The lesson. The cheapest time to find a gap in a tender is before you price it.
What we did. Before anything was priced, we read the full pack and wrote a 19-page review: 18 ambiguities listed, 13 risks, 16 qualifications to price against, 8 documents to request and 7 decisions for the owner.